Question: 1 / 220

Which aspect is crucial for the accountability of Developers in Scrum?

Managing the Product Owner's expectations

Delivering a working increment each Sprint

The aspect that is crucial for the accountability of Developers in Scrum is delivering a working increment each Sprint. In Scrum, the Developers are responsible for producing increments of valuable, usable software that meets the agreed Definition of Done at the end of each Sprint. This accountability is a core tenet of the Scrum framework, as it emphasizes the importance of transparency, inspection, and adaptation.

By delivering a usable product increment regularly, Developers provide stakeholders with tangible progress and foster trust in the team's ability to meet its commitments. This approach ensures that the team continually adds value and can adapt to changes based on feedback, keeping the project aligned with customer needs and expectations.

The other options do hold importance in the Scrum framework but do not directly pertain to the accountability of Developers. Managing the Product Owner's expectations is more about stakeholder engagement and communication. Setting up meeting agendas contributes to effective collaboration but is more of a facilitative role than a core accountability. Documenting all processes can help in maintaining clarity and continuity, yet it is not the primary focus of Developers' accountability.

Get further explanation with Examzify DeepDiveBeta

Setting up the meeting agendas

Documenting all processes